GNWT-AC (Aurora Campus - Inuvik) - OA-2022-001-AC

Well abandonment.

Documents

Displaying items 1 - 49 of 49
E.g., 10/11/2024
E.g., 10/11/2024

1. Authorizations, Well Approvals, and other Decisions

Authorization
Document Received/Sent Uploaded
2024-10-07 - Decision - Variation 1 - OA-2022-001-AC.pdf October 7, 2024 October 8, 2024
2023-09-28 - Decision - OA-2022-001-AC.pdf September 28, 2023 September 28, 2023
Other
Document Received/Sent Uploaded
2023-07-31 - Decision - Exemption from Cement Evaluation - Denied.pdf July 31, 2023 August 1, 2023
2023-06-02 - Decision - Amount of Proof of Financial Responsibility - OA-2022-001-AC.docx.pdf June 2, 2023 June 2, 2023
2023-04-20 - Decision - Abandonment Deadline Extension Denied.docx.pdf April 20, 2023 April 21, 2023

2. Initial Application

Application and Supporting Documents
Document Received/Sent Uploaded
2023-09-27 - from ITI - Benefits Plan Approval Confirmation - Aurora College Well G-04.pdf September 27, 2023 September 27, 2023
2022-12-12 - Application - Consolidated - OA-2022-001-AC.pdf December 12, 2022 December 12, 2022
Information Requests and Responses
Document Received/Sent Uploaded
2023-08-18 - from AC - Response to questions raised during meeting August 11, 2023 - OA-2022-001-AC.pdf August 18, 2023 August 21, 2023
2023-08-03 - IR6 - Response - OA-2022-001-AC - Aug_3_2023.pdf August 3, 2023 August 4, 2023
2023-08-04 - IR7 - Response - OA-2022-001-AC - CPE response August 4 2023.pdf August 4, 2023 August 4, 2023
2023-07-25 - IR6 - Response - OA-2022-001-AC.pdf July 25, 2023 July 27, 2023
2023-07-27 - IR7 - OA-2022-001-AC.docx.pdf July 27, 2023 July 27, 2023
2023-07-11 - IR6 - OA-2022-001-AC.pdf July 11, 2023 July 12, 2023
2023-06-16 - IR5 - Response - OA-2022-001-AC - updated with insurance certificate.pdf June 16, 2023 June 19, 2023
2023-06-06 - IR5 - OA-2022-001-AC.docx.pdf June 6, 2023 June 9, 2023
2023-05-26 - IR4 - Response - REDACTED - OA-2022-001-AC.pdf May 26, 2023 May 30, 2023
2023-05-17 - IR4 - OA-2022-001-AC.docx.pdf May 17, 2023 May 18, 2023
2023-05-01 - IR3 - Response - REDACTED - OA-2022-001-AC - Consolidated for public registry.pdf May 1, 2023 May 3, 2023
2023-03-14 - IR3 - Overdue - OA-2022-001-AC.docx.pdf March 14, 2023 March 14, 2023
2023-03-xx - IR3 - OA-2022-001-AC.docx.pdf March 3, 2023 March 6, 2023
2023-03-01 - IR2 - Response - Full OA Application with CPE Cover letter, Rev 2 Feb 25 2023.pdf March 1, 2023 March 2, 2023
2023-02-28 - IR2 - Overdue - EPP and SP - OA-2022-001-AC.docx.pdf February 28, 2023 February 28, 2023
2023-02-06 - IR1 - Response - CPE cover letter, Full OA Application 2022, Rev 1 Feb 5 2023.pdf February 6, 2023 February 6, 2023
2023-02-02 - to CPE - Acknowledgement of Proposed Response Schedule.pdf February 2, 2023 February 6, 2023
2023-01-29 - IR1 - Response - CPE Letter to OROGO for Aurora College abandonment Jan 29, 2023.pdf January 29, 2023 January 30, 2023
2023-01-06 - IR1 - Overdue - PFR Benefits Plan and Safety Plan.pdf January 6, 2023 January 6, 2023
2022-12-16 - IR1 - PFR Benefits Plan and Safety Plan.pdf December 16, 2022 December 16, 2022
Notices to MVEIRB
Document Received/Sent Uploaded
2023-02-16 - to MVEIRB - Preliminary Screening Determination - OA-2022-001-AC.pdf February 16, 2023 February 16, 2023
2022-12-12 - to MVEIRB - Notification of OA Application OA-2022-001-AC.pdf December 12, 2022 December 12, 2022
Orders and Directions
Document Received/Sent Uploaded
2023-04-20 - Direction - Response and Abandonment Deadlines.pdf April 20, 2023 April 21, 2023
2023-03-28 - Direction - IR3 - Overdue - OA-2022-001-AC.pdf March 28, 2023 March 31, 2023
2023-01-13 - Direction - IR1 - PFR Benefits Plan and Safety Plan.pdf January 13, 2023 January 13, 2023
Other
Document Received/Sent Uploaded
2023-07-07 - from AC - Request to delay G-04 abandonment and for exemptions to requirements.pdf July 7, 2023 July 14, 2023
2023-06-22 - from AC - Request for an alternative PFR - OA-2022-001-AC.pdf June 22, 2023 June 26, 2023
2023-06-26 - Decision - Alternative Form of PFR - OA-2022-001-AC.docx.pdf June 26, 2023 June 26, 2023
2023-06-14 - from AC - Request for extension for submission of PFR - OA-2022-001-AC.pdf June 14, 2023 June 16, 2023
2023-06-15 - Decision - Extension of Deadline for PFR to July 5 2023 - OA-2022-001-AC.pdf June 15, 2023 June 16, 2023
2023-04-24 - from AC - CPE response to Direction of OROGO 23 04 24.pdf April 24, 2023 April 26, 2023
2023-04-13 - from AC - Extension Request - OA-2022-001-AC - Training Well G-04 WID 1915.pdf April 13, 2023 April 19, 2023