Suncor Energy Inc. - OA-2021-003-SUN - Colville area
Status:
Approved
Activity:
Operations (OA)
Start:
Expiry:
November 1, 2024
Abandonment
Documents
Displaying items 1 - 27 of 27
1. Authorizations, Well Approvals, and other Decisions
Document | Received/Sent | Uploaded |
---|---|---|
2023-01-18 - Decision - Variation 1 - OA-2021-003-SUN.pdf | January 18, 2023 | January 19, 2023 |
2022-10-07 - Decision - OA-2021-003-SUN.pdf | October 7, 2022 | October 12, 2022 |
Document | Received/Sent | Uploaded |
---|---|---|
2022-10-06 - Decision - to MVEIRB - Determination of Preliminary Screening OA-2021-003-SUN.docx.pdf | October 6, 2022 | October 12, 2022 |
Document | Received/Sent | Uploaded |
---|---|---|
2022-12-19 - Decision - Deferral of Sahtu Abandonments to March 31 2025.docx.pdf | December 19, 2022 | December 19, 2022 |
2022-08-05 - Decision - Amount of Proof of Financial Responsibility OA-2021-003-SUN.docx.pdf | August 5, 2022 | August 8, 2022 |
2021-12-20 - Decision - to SUN - Extension of Abandonment Deadline to Mar 31 2024 - OA-2021-003-SUN.pdf | December 20, 2021 | December 20, 2021 |
2. Initial Application
Document | Received/Sent | Uploaded |
---|---|---|
2021-05-31 - Application - Suncor Colville OA - redacted.pdf | May 31, 2021 | June 4, 2021 |
Document | Received/Sent | Uploaded |
---|---|---|
2021-06-08 - Notification - To MVEIRB - OA Application Received from Suncor OA-2021-003-SUN.pdf | June 8, 2021 | October 4, 2021 |
Document | Received/Sent | Uploaded |
---|---|---|
2021-07-20 - Decision - to SUN - Extension for Response to IR No 2 - OA-2021-003-SUN.pdf | July 20, 2021 | October 4, 2021 |
3. Amendment Applications
Document | Received/Sent | Uploaded |
---|---|---|
2023-06-08 - from SUN - Extension Request - OA-2021-003-SUN - Colville Lake Deferral Letter.pdf | June 8, 2023 | June 9, 2023 |
2022-12-12 - Application - Variation - Suncor Request for Deferral Colville Lake.pdf | December 14, 2022 | December 14, 2022 |
Document | Received/Sent | Uploaded |
---|---|---|
2023-09-12 - IR6 - Variation 2 - OA-2021-003-SUN.docx.pdf | September 12, 2023 | September 14, 2023 |
2023-07-14 - IR5 - Response - OA-2021-003-SUN.pdf | July 14, 2023 | July 18, 2023 |
2023-06-26 - Decision - Extension of Deadline for IR5 to July 16 2023 - OA-2021-003-SUN.pdf | June 26, 2023 | June 27, 2023 |
2023-06-14 - IR5 - Variation 2 - OA-2021-003-SUN.docx.pdf | June 14, 2023 | June 16, 2023 |
4. Compliance and Enforcement
Document | Received/Sent | Uploaded |
---|---|---|
2021-12-03 - to SUN - Execution Plan for 2022-23 Abandonments - OA-2021-003-SUN.docx.pdf | December 3, 2021 | December 3, 2021 |