Strategic Oil and Gas Ltd. - OA-2018-003-SOG
Status:
Approved
Activity:
Operations (OA)
Start:
March 20, 2019 ?>
Expiry:
April 1, 2025
Maintenance and abandonment
Documents
Displaying items 1 - 100 of 107
1. Authorizations, Well Approvals, and other Decisions
Document | Received/Sent | Uploaded |
---|---|---|
2021-02-01 - Decision - to Strategic - Approval of Amended OA - OA-2018-003-SOG - variation 2.pdf | February 1, 2021 | February 1, 2021 |
2020-03-13 - Decision - to AM - Approval for A-03 Pipeline Deactivation - OA-2018-003-SOG.pdf | March 13, 2020 | May 27, 2020 |
2019-03-20 - Decision - to Strategic - Application for an Operations Authorization for the Cameron Hills Field.pdf | March 20, 2019 | March 31, 2020 |
Document | Received/Sent | Uploaded |
---|---|---|
2023-09-14 - Decision - Variation to Multiple Approvals - Extension to GM Testing Deadline.pdf | September 14, 2023 | September 15, 2023 |
2022-10-03 - Decision - Request to Delay Cameron Hills Abandonments.pdf | October 3, 2022 | October 3, 2022 |
2021-07-09 - Decision - to SOG - Abandonment Plan for Suspended Wells - OA-2018-003-SOG.docx.pdf | July 9, 2021 | July 9, 2021 |
2019-04-17 - Decision - to SOG - Variation to OA for the Cameron Hills Field OA-2018-003-SOG.pdf | April 17, 2019 | March 31, 2020 |
2. Initial Application
Document | Received/Sent | Uploaded |
---|---|---|
2018-11-09 - Application - SOG Operations Authorization Application Package.pdf | November 9, 2018 | March 31, 2020 |
2018-11-09 - Application - SOG Operations Authorization Application Package - Additional Documents.pdf | November 9, 2018 | March 31, 2020 |
Document | Received/Sent | Uploaded |
---|---|---|
2019-03-20 - to MVEIRB - Preliminary Screening - SOG Application for an Operations Authorization.pdf | March 20, 2019 | March 31, 2020 |
2018-11-22 - to MVEIRB - Notification of OA Application Received.pdf | November 22, 2018 | March 31, 2020 |
3. Amendment Applications
Document | Received/Sent | Uploaded |
---|---|---|
2022-09-19 - Request - From SOG - Extension Request - Abandonment Plan for Suspended Wells – OA-2018-003-SOG.pdf | September 19, 2022 | September 20, 2022 |
2021-07-06 - from AM - Request for Extension to the Abandonment Plan for Suspended Wells – OA-2018-003-SOG.pdf | July 6, 2021 | July 9, 2021 |
2021-01-27 – Plan – Revised Abandonment Plan for Suspended Wells – OA-2018-003-SOG.pdf | January 27, 2021 | January 28, 2021 |
2020-03-13 - Application- to Deactivate Pipeline - H03 to A03 Pipeline Cameron Hills SOG-NWT_000145.pdf.pdf | March 13, 2020 | May 27, 2020 |
Document | Received/Sent | Uploaded |
---|---|---|
2021-02-01 - to MVEIRB - Preliminary Screening Determination - Approval Amended OA -OA-2018-003-SOG variation 2.pdf | February 1, 2021 | February 1, 2021 |
Document | Received/Sent | Uploaded |
---|---|---|
2022-09-21 - to SOG - Response to Extension Request by Oct 3 2022.pdf | September 21, 2022 | September 22, 2022 |
2019-04-09 - from SOG - Request for OA-2018-003-SOG Erp Update Extension.pdf | April 9, 2019 | March 31, 2020 |
4. Compliance and Enforcement
Document | Received/Sent | Uploaded |
---|---|---|
2023-02-06 - Incident - Summary Report - FILE CLOSED - to SOG - Worker struck by pressurized hose at H-03 Battery.docx.pdf | February 6, 2023 | February 6, 2023 |
2023-01-09 - Incident - Summary Report - Pressurized hose strikng worker.docx.pdf | January 9, 2023 | January 10, 2023 |
2019-09-24 - Incident - I-73 Gas Leak.pdf | September 24, 2019 | March 31, 2020 |
Document | Received/Sent | Uploaded |
---|---|---|
2024-09-25 - Notice - Concerns identified in Cameron Hills during September 17-19 2024 inspections.pdf | September 25, 2024 | October 3, 2024 |
2024-10-02 - Notice - Concerns identified in Cameron Hills during September 17-19 2024 inspections.pdf.pdf | October 2, 2024 | October 3, 2024 |
2024-06-10 - Notice - Cameron Hills Remaining Environmental Liabilities.pdf | June 10, 2024 | June 11, 2024 |
2024-02-23 - Notice - To SOG - Spill Reporting Requirement – Gas Migration and Surface Casing Vent Flow.pdf | February 23, 2024 | February 23, 2024 |
2022-06-01 - Notice - To SOG - Overdue Emergency Response Plan.docx.pdf | June 1, 2022 | June 15, 2022 |
2021-06-09 - Notice - To SOG - Outstanding Emergency Response Plan.pdf | June 9, 2021 | June 11, 2021 |
Document | Received/Sent | Uploaded |
---|---|---|
2019-10-04 - Order - to Strategic - Abandonment and Decommissioning.pdf | October 4, 2019 | March 31, 2020 |
Document | Received/Sent | Uploaded |
---|---|---|
2023-11-08 - to AM - Simplified OL Renewal Process.docx.pdf | November 8, 2023 | November 15, 2023 |
2023-08-08 - Notification - from SOG - GM Test Notification - August 18-24, 2023.pdf | August 8, 2023 | August 21, 2023 |
2022-03-29 - from SOG - Request for Extension to Submit Annual Environmental Report – OA-2018-003-SOG.pdf | March 29, 2022 | March 29, 2022 |
2022-03-29 - Decision - Approved extension of deadline for submission of annual reports to May 3.pdf | March 29, 2022 | March 29, 2022 |
2021-12-02 - to Strategic - Execution Plan for 2022-23 Abandonments - OA-2018-003-Strategic.pdf | December 2, 2021 | December 2, 2021 |
2019-11-26 - to SOG - Suspended Non-Compliant Cameron C-19 Well - WID 1767 - OA-2018-003-SOG.pdf | November 26, 2019 | March 31, 2020 |
5. Reports and Studies
Document | Received/Sent | Uploaded |
---|---|---|
2021-06-17 - ERP - AM _ Strategic ERP - June 2021 - redacted.pdf | June 17, 2021 | June 17, 2021 |