Strategic Oil and Gas Ltd. - ACW-2022-SOG-M-31-WID1122

Abandonment

Documents

Displaying items 1 - 28 of 28
E.g., 03/29/2024
E.g., 03/29/2024

1. Authorizations, Well Approvals, and other Decisions

Other
Document Received/Sent Uploaded
2024-02-09 - Decision - Variation 5 - ACW-2022-SOG-M-31-WID1122.docx.pdf February 9, 2024 February 13, 2024
2024-01-15 - Decision - Variation 4 - ACW-2022-SOG-M-31-WID1122.docx.pdf January 15, 2024 January 23, 2024
2023-10-13 - Approval - Variation 3 - ACW-2022-SOG-M-31-WID1122.docx.pdf October 13, 2023 October 16, 2023
Well Approval
Document Received/Sent Uploaded
2023-03-10 - Decision - Variation 2 - ACW-2022-SOG-M-31-WID1122.docx.pdf March 10, 2023 March 10, 2023
2023-01-04 - Decision - Variation 1 - ACW-2022-SOG-M-31-WID1122.docx.pdf January 4, 2023 January 4, 2023
2022-06-13 - Decision - Approval ACW-2022-SOG-M-31-WID1122.pdf June 13, 2022 June 15, 2022

2. Initial Application

Application and Supporting Documents
Document Received/Sent Uploaded
2022-06-10 - Application - ACW-2022-SOG-M-31-WID1122 - ACW for Abandonment Application - June 10, 2022.pdf June 10, 2022 June 15, 2022
Information Requests and Responses
Document Received/Sent Uploaded
2022-12-20 - IR1 - Supplementary Response - REDACTED - Cameron M-31 v2.pdf December 20, 2022 December 21, 2022

3. Amendment Applications

4. Compliance and Enforcement

Incident or Near-Miss Reports
Document Received/Sent Uploaded
INC-2024-001-SOG-OA-2018-003.pdf March 28, 2024 March 28, 2024
Inspection Report
Document Received/Sent Uploaded
2024-02-14 - Report - to SOG - Inspection by OROGO - Operations Summary Inspection Report M-31 (WID 1122)_.pdf February 14, 2024 February 15, 2024
2023-10-15 - Inspection - by SOG - Cameron M-31 WID 1122.pdf October 15, 2023 November 24, 2023
2023-03-16 - Inspection - By OROGO - Operations Summary Inspection Report M-31 (WID 1122).pdf March 16, 2023 March 17, 2023
2023-03-03 - Inspection - By OROGO - Operations Summary Inspection Report M-31 (WID 1122).pdf March 3, 2023 March 6, 2023
2022-10-28 - Inspection - by SOG - GM Testing - 22453 TB Oct 28-22 REPORT Heli Source Cameron Hills M-31.pdf December 19, 2022 December 19, 2022
2022-09-19 - Inspection - by SOG - M-31 Well Inspection Report 2022 (Receiver).pdf December 7, 2022 December 7, 2022
2022-09-15 - Inspection - by SOG - GM Testing - 22316 TB Sept 15-22 REPORT Heli Source Cameron Hills M-31.pdf November 17, 2022 November 17, 2022
2022-10-12 - Inspection Report - Cameron M-31 (WID1122) OROGO Well Inspection Report Form.docx.pdf October 12, 2022 October 12, 2022
Notices
Document Received/Sent Uploaded
2022-11-23 - Notice - to SOG - Variation Requirement for Gas Migration - Cameron M-31 Well - WID 1122.docx.pdf November 23, 2022 November 23, 2022
Other
Document Received/Sent Uploaded
2024-03-11 - Change of Status - Cameron M-31 Compliant-Suspended.docx.pdf March 11, 2024 March 12, 2024
2023-11-28 - to SOG - GM Testing NOT Satisfactory - Cameron M-31.docx.pdf November 28, 2023 November 29, 2023
2023-07-06 - Change of Status - Cameron M-31 Compliant-Suspended.docx.pdf July 6, 2023 July 7, 2023
2022-11-23 - to SOG - Change of Well Status - Non-Compliant Suspended - Cameron Hills M-31 Well WID 1122.docx.pdf November 23, 2022 November 23, 2022