Paramount Resources Ltd. - ACW-2022-PAR-B-41-WID1733
Status:
Expired
Activity:
Alter Condition of a Well (ACW)
Start:
July 25, 2022 ?>
Expiry:
November 1, 2023
Abandonment
Documents
Displaying items 1 - 16 of 16
1. Authorizations, Well Approvals, and other Decisions
Document | Received/Sent | Uploaded |
---|---|---|
2023-05-10 - Change of Well Status - Abandonment of Arrowhead River B-41 WID1733.docx.pdf | May 10, 2023 | May 11, 2023 |
Document | Received/Sent | Uploaded |
---|---|---|
2022-07-25 - Decision - Approval of ACW-2022-PAR-B-41-WID1733.pdf | July 25, 2022 | July 26, 2022 |
2. Initial Application
Document | Received/Sent | Uploaded |
---|---|---|
2022-04-29 - Form - Paramount et al Arrowhead River B-41 WID 1733 AACW Form.pdf | April 29, 2022 | May 3, 2022 |
2022-04-29 - Program - Application for ACW - Arrowhead B-41 WID 1733 - with attachments - REDACTED.pdf | April 29, 2022 | May 3, 2022 |
Document | Received/Sent | Uploaded |
---|---|---|
2022-07-13 - IR3 - from PAR - Updated Abandonment Program.pdf | July 13, 2022 | July 15, 2022 |
2022-06-15 - IR3 - Remedial Cementing Feed Rates - ACW-2022-PAR-B-41-WID1733.docx.pdf | June 15, 2022 | June 16, 2022 |
2022-06-07 - IR2 - from PAR - Updated Program and Application Form - ACW-2022-PAR-B-41-WID1733.pdf | June 7, 2022 | June 8, 2022 |
2022-06-03 - IR2 - Remedial Cementing Steps - ACW-2022-PAR-B-41-WID1733.docx.pdf | June 3, 2022 | June 6, 2022 |
2022-05-27 - IR1 - from PAR - Updated Program and Application Form.pdf | May 27, 2022 | May 27, 2022 |
2022-05-18 - from PAR - Extension Request - LTR ACW IRs Liard East Arrowhead OA-2020-001-PAR, 18-May-2022.pdf | May 18, 2022 | May 20, 2022 |
2022-05-18 - Decision - Extension of IR1 Deadline to June 29 2022 - ACW-2022-PAR-B-41-WID1733.pdf | May 18, 2022 | May 20, 2022 |
2022-05-03 - IR1 - Updated Program Requirements - ACW-2022-PAR-B-41-WID1733.docx.pdf | May 3, 2022 | May 3, 2022 |
4. Compliance and Enforcement
Document | Received/Sent | Uploaded |
---|---|---|
2023-02-15 - Inspection - By OROGO - Operations Summary Inspection Report B-41 (WID 1733).docx.pdf | February 15, 2023 | February 15, 2023 |
2022-07-21 - Inspection - by OROGO - Arrowhead River B-41 WID1733.pdf | July 21, 2022 | January 13, 2023 |
2022-07-21 - Inspection - by PAR - Arrowhead B-41 WID 1773 SWI GMT Report.pdf | July 21, 2022 | August 25, 2022 |
Document | Received/Sent | Uploaded |
---|---|---|
2023-02-22 - Form - Change of Well Status - Arrowhead B-41 WID1733.pdf | February 22, 2023 | May 11, 2023 |