Paramount Resources Ltd. - ACW-2022-PAR-2K-29-WID1980
Status:
Expired
Activity:
Alter Condition of a Well (ACW)
Start:
April 12, 2023 ?>
Expiry:
November 1, 2023
Abandonment
Documents
Displaying items 1 - 15 of 15
1. Authorizations, Well Approvals, and other Decisions
Document | Received/Sent | Uploaded |
---|---|---|
2023-12-12 - Change of Status - Liard 2K-29 Abandoned.docx.pdf | December 12, 2023 | December 14, 2023 |
2023-08-04 - Decision - Variation 1 - ACW-2022-PAR-2K-29-WID1980.pdf | August 4, 2023 | August 4, 2023 |
2022-10-28 - Decision - Use of Coiled Tubing Unit on Shallow Wellbore Plugs.docx.pdf | October 28, 2022 | October 31, 2022 |
Document | Received/Sent | Uploaded |
---|---|---|
2023-04-12 - Decision - ACW-2022-PAR-2K-29-WID1980.docx.pdf | April 12, 2023 | April 12, 2023 |
2. Initial Application
Document | Received/Sent | Uploaded |
---|---|---|
2022-08-15 - Application - Liard 2K-29 Well Abandonment.pdf | August 15, 2022 | August 15, 2022 |
Document | Received/Sent | Uploaded |
---|---|---|
2022-11-30 - IR3 - Response - 2022-Nov_2K-29 60 30 123 30 PRL ABD Program (IR3 Revision).pdf | November 30, 2022 | December 1, 2022 |
2022-10-31 - IR3 - Updated Program Requirements - ACW-2022-PAR-2K-29-WID1980.docx.pdf | October 31, 2022 | November 1, 2022 |
2022-10-19 - IR2 - Response - ACW-2022-PAR-2K-29-WID1980.pdf | October 20, 2022 | October 20, 2022 |
2022-10-05 - IR2 - Updated Program Requirements - ACW-2022-PAR-2K-29-WID1980.docx.pdf | October 5, 2022 | October 5, 2022 |
2022-08-26 - IR1 - Response - 2022-Aug_2K-29 60 30 123 30 PRL ABD Program.pdf | August 26, 2022 | August 26, 2022 |
2022-08-15 - IR1 - Updated Program Requirements - ACW-2022-PAR-2K-29-WID1980.docx.pdf | August 15, 2022 | August 15, 2022 |
3. Amendment Applications
Document | Received/Sent | Uploaded |
---|---|---|
2023-08-04 - from PAR - Variation 1 - Paramount et al Laird 2K-29 WID 1980 Variation Request.pdf | August 4, 2023 | August 4, 2023 |
4. Compliance and Enforcement
Document | Received/Sent | Uploaded |
---|---|---|
2023-08-01 - Inspection - OROGO Operations Inspection Report Liard 2K-29 WID1980.pdf | August 9, 2023 | August 9, 2023 |
2022-07-20 - Inspection - by OROGO - Liard 2K-29 WID1980.pdf | July 20, 2022 | January 13, 2023 |
2022-08-24 - Inspection - by PAR - 2K-29 WID1980 SWI and GM August 24 2022.pdf | November 15, 2022 | November 16, 2022 |