Canadian Natural Resources Limited - ACW-2019-012-CNRL-I-75-WID1981

Abandonment activities

Documents

Displaying items 1 - 28 of 28
E.g., 10/11/2024
E.g., 10/11/2024

1. Authorizations, Well Approvals, and other Decisions

3. Amendment Applications

Amendment Request and Supporting Documents
Document Received/Sent Uploaded
2022-12-12 - Application - Variation - 300-I-75-60.40-122.45-00 (WID1981) Abandonment Program - Variation 1.pdf December 12, 2022 December 12, 2022

4. Compliance and Enforcement

Inspection Report
Document Received/Sent Uploaded
2023-07-18 - Report - Gas Migration Testing - I-75 - NT1981_GM_2023JUL18_NO_EMISSION_SIGNED.pdf July 18, 2023 July 27, 2023
2023-02-15 - Inspection - By OROGO - Operations Summary Inspection Report I-75 (WID 1981).pdf February 15, 2023 February 15, 2023
2022-07-20 - Inspection - by OROGO - Arrowhead River J-74 WID1987.pdf July 20, 2022 January 12, 2023
2022-07-20 - Inspection - by OROGO - Arrowhead River I-75 WID1981.pdf July 20, 2022 January 12, 2023
2022-05-18 - Gas Migration - NT1981_GM_2022MAY18_I-75_PASS.pdf December 1, 2022 December 2, 2022
2022-09-12 - Inspection - by CNRL - Arrowhead River I-75 WID1981.pdf October 11, 2022 October 12, 2022
2022-05-18 - Inspection - by CNRL - Arrowhead River I-75 - WID 1981.pdf June 9, 2022 June 16, 2022
2022-02-23 - Inspection - By OROGO - Arrowhead River I-75 - WID 1981 Inspection Summary Report.pdf March 18, 2022 March 18, 2022
2021-03-29 - Inspection - by CNRL - Arrowhead River I-75 - WID 1981.pdf March 29, 2021 January 20, 2022
2020-12-03 - Inspection - by CNRL - Arrowhead River I-75 - WID 1981.pdf December 3, 2020 January 20, 2022
2021-07-14 - Inspection - by CNRL - Arrowhead River I-75 - WID 1981.pdf July 14, 2021 January 20, 2022
Other
Document Received/Sent Uploaded
2023-07-31 - to CNRL - Requirements Complete - ACW-2019-012-CNRL-I-75-WID1981.pdf July 31, 2023 August 1, 2023
2023-06-07 - Form - Change of Well Status - Arrowhead River I-75 WID 1981.pdf June 7, 2023 June 13, 2023