Canadian Natural Resources Limited - ACW-2019-011-CNRL-P-16-WID1976
Status:
Expired
Activity:
Alter Condition of a Well (ACW)
Start:
May 13, 2020 ?>
Expiry:
August 13, 2024
Abandonment Activities
Documents
Displaying items 1 - 42 of 42
1. Authorizations, Well Approvals, and other Decisions
Document | Received/Sent | Uploaded |
---|---|---|
2020-05-13 - Decision - to CNRL - Approval of Abandonment of Liard P-16 Well.docx.pdf | May 13, 2020 | June 4, 2020 |
2. Initial Application
Document | Received/Sent | Uploaded |
---|---|---|
2019-10-30 - Application - ANADARKO LIARD P-16 (NT001976).pdf | October 30, 2019 | June 4, 2020 |
2020-02-28 - Application - Supporting Documents - ACW - LIARD P-16 (NT001976) - Compiled.pdf | February 28, 2020 | June 4, 2020 |
Document | Received/Sent | Uploaded |
---|---|---|
300-P-16-60.30-123.30-00 (WID1976) Abandonment Program - IR1 update.pdf | April 27, 2020 | June 4, 2020 |
Liard P-16 well (ACW-2019-011-CNRL-P-16-WID1976) - IR1 response.pdf | April 27, 2020 | June 4, 2020 |
2020-03-27 - IR1 - to CNRL - Well Abandonment Program Procedures - ACW-2019-011-P-16-WID1976.pdf | March 27, 2020 | April 8, 2020 |
3. Amendment Applications
Document | Received/Sent | Uploaded |
---|---|---|
2023-08-15 - from CNRL - Variation 9 - ACW_2019-001-CNRL-P-16-WID1976.pdf | August 15, 2023 | August 16, 2023 |
2023-08-03 - from CNRL - Variation Request 8 - ACW_2019-001-CNRL-P-16-WID1976.pdf | August 3, 2023 | August 4, 2023 |
2023-07-19 - from CNRL - Request for Variation - Time Sensitive - BP depth Revision.pdf | July 19, 2023 | July 20, 2023 |
2023-07-16 - from CNRL - Request for Variation - CNRL P-16 Time Sensitive Jet Cut Proposal to cut higher.pdf | July 16, 2023 | July 18, 2023 |
2023-07-12 - Application - REDACTED - Variation 5 - P-16 (WID1976) Abandonment Program July 2023.pdf | July 12, 2023 | July 14, 2023 |
2023-06-23 - Application - Variation 4 - REDACTED - P-16 (WID1976) Abandonment Program.pdf | June 23, 2023 | June 26, 2023 |
2022-12-07 - from CNRL - Request to Defer Abandonment - Liard P-16 Wellsite.pdf | December 7, 2022 | December 8, 2022 |
Document | Received/Sent | Uploaded |
---|---|---|
2023-09-01 - from CNRL - Extension Request - P-16 abandonment extension request August 31, 2023.pdf | September 1, 2023 | September 5, 2023 |
4. Compliance and Enforcement
Document | Received/Sent | Uploaded |
---|---|---|
INC-2024-002-CNRL-OA-2018-005.pdf | August 13, 2024 | March 28, 2024 |
Document | Received/Sent | Uploaded |
---|---|---|
2023-12-11 - to CNRL - Liard P-16 Reporting Satisfactory.pdf | December 11, 2023 | December 13, 2023 |
5. Reports and Studies
Document | Received/Sent | Uploaded |
---|---|---|
2023-07-10 - Report - Gas Migration Testing - P-16 July 2023.pdf | July 10, 2023 | October 12, 2023 |
Document | Received/Sent | Uploaded |
---|---|---|
2024-06-12 - Report - by CNRL - SCVF Testing - NT001976_SCVF_TEST_2024JUN12_NO_FLOW_SIGNED.pdf | June 18, 2024 | June 25, 2024 |