Canadian Natural Resources Limited - ACW-2019-009-CNRL-K-77-WID1862
Status:
Approved
Activity:
Alter Condition of a Well (ACW)
Start:
May 13, 2020
Expiry:
November 1, 2023
Abandonment activities
Documents
Displaying items 1 - 18 of 18
1. Authorizations, Well Approvals, and other Decisions
Document | Received/Sent | Uploaded |
---|---|---|
2022-12-07 - Decision - Variation 4 - ACW-2019-009-CNRL-K-77-WID1862.docx.pdf | December 7, 2022 | December 7, 2022 |
2020-12-17 - Decision - Variation 2 - ACW-2019-009-CNRL-K-77-WID1862.pdf | December 17, 2020 | July 6, 2022 |
2020-07-07 - Decision - Variation 1 - ACW-2019-009-CNRL-K-77-WID1862.pdf | July 7, 2020 | July 6, 2022 |
2022-07-06 - Decision - Variation 3 - ACW-2019-009-CNRL-K-77-WID1862.docx.pdf | July 6, 2022 | July 6, 2022 |
2020-05-13 - Decision - to CNRL - Approval of Abandonment of Netla K-77 Well.docx.pdf | May 13, 2020 | June 4, 2020 |
2. Initial Application
Document | Received/Sent | Uploaded |
---|---|---|
2019-10-30 - Application - SUNCOR NETLA K-77 (NT001862 WV - NT003037 AM).pdf | February 27, 2020 | June 4, 2020 |
2020-02-27 - Application - Supporting Documentation - ACW - NETLA K-77 (NT001862) - Compiled.pdf | February 27, 2020 | June 4, 2020 |
Document | Received/Sent | Uploaded |
---|---|---|
300-K-77-60.50-122.30-00 (WID1862) Abandonment Program - IR1 update.pdf | April 27, 2020 | June 4, 2020 |
Netla K-77 well (ACW-2019-009-CNRL-K-77-WID1862) - IR1 response.pdf | April 27, 2020 | June 4, 2020 |
2020-03-27 - IR1 - to CNRL - Well Abandonment Program Procedures - ACW-2019-009-K-77-WID1862.pdf | March 27, 2020 | April 8, 2020 |
4. Compliance and Enforcement
Document | Received/Sent | Uploaded |
---|---|---|
2022-07-20 - Inspection - by OROGO - Netla K-77 WID1862.pdf | July 20, 2022 | January 12, 2023 |
2022-05-18 - Gas Migration - NT1862_GM_2022MAY18_K-77PASS.pdf | December 1, 2022 | December 2, 2022 |
2022-09-12 - Inspection - by CNRL - Netla K-77 WID1862.pdf | October 11, 2022 | October 12, 2022 |
2022-05-18 - Inspection - by CNRL - Netla K-77 - WID 1862.pdf | June 9, 2022 | June 16, 2022 |
2022-02-23 - Inspection - By OROGO - Netla K-77 WID 1862 Inspection Summary Report.pdf | March 18, 2022 | March 18, 2022 |
2021-07-14 - Inspection - by CNRL - Netla K-77 - WID 1862 - REDACTED - with SCVF test.pdf | July 14, 2021 | January 20, 2022 |
2021-03-29 - Inspection - by CNRL - Netla K-77 - WID 1862 - with gas analysis.pdf | March 29, 2021 | January 20, 2022 |
2020-12-03 - Inspection - by CNRL - Netla K-77 - WID 1862.pdf | December 3, 2020 | January 20, 2022 |